What If Both Parties Breach the Contract? Article 1192 Explained
Quick answer: When both parties to a reciprocal contract breach it, Article 1192 of the Civil Code looks at who broke the contract first. The first infractor stays liable for damages, but the court may equitably reduce that liability. The second infractor is generally not liable for damages at all, because the harm from the second breach is offset by reducing the first infractor’s liability. If no one can tell who breached first, the contract is deemed extinguished and each party bears its own damages.
The Supreme Court explained this reading in Ong v. Bogñalbal, G.R. No. 149140 (September 12, 2006), a dispute between a shop owner who stopped paying a progress billing and a contractor who then walked off the job. This guide explains how the rule works, what evidence decides the sequence of breaches, and what to do if you are on either side.
Article 1192 at a glance
- Rule: the first infractor is liable, but its liability “shall be equitably tempered by the courts” (Civil Code, Art. 1192).
- Exception: if the first breach cannot be determined, the contract is deemed extinguished and each party bears its own damages.
- Evidence: a dated record of what each side had to do, when, and what each actually did.
- Deadline and forum: no special period is set by Article 1192 itself; the claim follows the ordinary prescriptive period for actions on the contract, filed in the court with jurisdiction over the amount or subject.
- Next step: build a chronology, identify the first non-performance, and send a written demand before suing.
What Article 1192 says
“In case both parties have committed a breach of the obligation, the liability of the first infractor shall be equitably tempered by the courts. If it cannot be determined which of the parties first violated the contract, the same shall be deemed extinguished, and each shall bear his own damages.”
Civil Code of the Philippines (Republic Act No. 386), Article 1192, as quoted in Ong v. Bogñalbal, G.R. No. 149140
The article applies only to reciprocal obligations, where each party’s promise is the reason for the other’s: price for goods, payment for construction work, rent for use of property. It sits right after Article 1191, which gives the injured party the choice between fulfillment and rescission (resolution), with damages in either case.
The first infractor pays, but the court may reduce it
In Ong v. Bogñalbal, the Court read Article 1192 this way: the second infractor “is not liable for damages at all,” because the damages it would have owed are “compensated instead by the mitigation of the first infractor’s liability.” The first infractor remains liable, but its liability is tempered because the second infractor also gained, or thought it would gain, from its own breach.
The Court also harmonized Article 1192 with Article 2215(1), which lets a court equitably mitigate damages when “the plaintiff himself has contravened the terms of the contract.” The plaintiff in Article 2215(1) is treated as the second infractor, and the party whose damages are reduced is the first infractor. Despite the word “shall” in Article 1192, how much to reduce is left to the court’s judgment of what is equitable.
Applied to the facts, the shop owner breached first by refusing to pay a progress billing that the contract’s third-party certification made due. She was liable for damages, subject to reduction. The contractor, who then abandoned the work without a court order, was the second infractor and was not liable on her counterclaim for damages.
When no one can tell who breached first
The second sentence of Article 1192 is a fallback. If the evidence does not show which party violated the contract first, the contract is deemed extinguished and each party bears its own damages. Neither side recovers damages from the other on the contract. This is why the sequence of events is usually the whole case: a party who cannot prove the other side broke the contract first risks walking away with nothing.
A caution where work or payment was only partly done
Ong v. Bogñalbal warned that Article 1192 presupposes the parties are on equal footing in their principal obligations. Where one or both have partly performed, actual damages representing deficiencies in performing the principal obligation should be taken out of the equation. In that case the contractor had finished more of the work than the owner had paid for, so he still recovered the value of the accomplished work that the owner had not paid. Article 1192 governs the damages for the breach; it does not wipe out what one side already earned through performance.
Walking away is often the second breach
Many “both parties breached” disputes start when one side stops performing because the other side breached. Ong v. Bogñalbal, quoting earlier rulings, repeated that the power to rescind under Article 1191 must be invoked judicially unless the contract allows rescission without going to court. A party who unilaterally terminates without such a clause acts without justification, and that act can itself be a breach. If your contract has no termination clause, the safer course after the other side’s breach is a written demand and, if needed, a court action, not simply stopping work.
Article 1169 adds a timing rule for reciprocal obligations: neither party incurs delay if the other does not comply or is not ready to comply in a proper manner, and from the moment one party fulfills its obligation, delay by the other begins (as quoted in Megaworld Globus Asia v. Tanseco, G.R. No. 181206). Showing that you performed or were ready to perform is therefore part of proving that the other side breached first.
Decision table
Use this to see where your facts likely fall under Article 1192.
| Situation | Likely result | Basis |
|---|---|---|
| Party A clearly breached first, then Party B breached | Party A liable for damages, possibly reduced; Party B not liable for damages | Art. 1192; Ong v. Bogñalbal |
| Both breached, order cannot be proven | Contract deemed extinguished; each bears own damages | Art. 1192, second sentence |
| One side partly performed before the breaches | Value of unpaid accomplished work may still be recovered | Ong v. Bogñalbal |
| Only one side actually breached | Article 1192 does not apply; ordinary Article 1191 remedies | Art. 1191 |
| A party stopped performing without a termination clause or court action | The stoppage may count as a breach | Ong v. Bogñalbal, quoting earlier rulings |
The table is a starting point. The court weighs the contract terms, what each obligation required, and when each failure happened.
Evidence that decides who breached first
- The contract and any written amendments, especially payment schedules, delivery dates, and conditions such as certifications or inspections.
- Billings, receipts, bank records and delivery receipts with dates.
- Emails, texts and letters showing when each side complained, refused or stopped.
- Demand letters and the replies, with proof of receipt.
- Proof that you performed or were ready to perform when the other side defaulted.
- Progress reports, photos and third-party certifications of work completed.
A claimed change to the contract must also be proven. In Ong v. Bogñalbal, the owner argued that payment was conditioned on finishing the flooring first, but she could not prove that the contract had been changed, so her refusal to pay was the first breach.
Your options and what to do next
If you believe the other side breached first
- Write a dated chronology of both parties’ obligations and what each did, attaching the documents above.
- Send a written demand identifying the breach, what you want (performance, refund or damages), and a reasonable deadline. Keep proof of delivery.
- Do not stop performing on your own unless the contract lets you terminate without going to court; otherwise you risk becoming an infractor yourself.
- If the other party does not respond, ask the barangay or the Public Attorney’s Office whether barangay conciliation is required before filing, then file an action for fulfillment or rescission with damages under Article 1191.
If you may have breached first
- Cure the breach promptly where you still can, and put the cure in writing.
- Gather proof of the other side’s later breach; it is the basis for asking the court to reduce your liability under Articles 1192 and 2215(1).
- Document any work or payment you already completed so its value is accounted for.
- Consider settlement: a written compromise that sets off both sides’ claims often costs less than litigating the sequence.
Frequently asked questions
Does Article 1192 cancel the contract automatically?
Only when it cannot be determined who breached first. In that case the contract is deemed extinguished and each party bears its own damages. When the first infractor is known, the contract consequences follow Article 1191 and the first infractor’s liability is tempered.
Can the second infractor still be ordered to pay anything?
Under Ong v. Bogñalbal, the second infractor is not liable for damages for its breach. That does not erase amounts it owes for performance already received, which the Court said should be separated from the Article 1192 analysis.
How much will the court reduce the first infractor’s damages?
There is no formula. The Court held that the reduction is discretionary and depends on what is equitable in the circumstances.
Is a late payment always the first breach?
Not necessarily. A payment is breached only if it was due. If the contract made payment depend on a condition, such as a certification or delivery, the question is whether that condition was met first.
Related CivilLaw.ph guides
- What counts as a substantial breach of contract
- Can delay alone be a substantial breach under Article 1191?
- Specific performance vs resolution vs damages
- Mutual restitution after resolution under Article 1191
- Do you need a demand letter before suing for breach?
Sources and legal citations
- Civil Code of the Philippines, Republic Act No. 386, Articles 1169, 1191, 1192 and 2215.
- Ong v. Bogñalbal, G.R. No. 149140, September 12, 2006.
- Megaworld Globus Asia, Inc. v. Tanseco, G.R. No. 181206, October 9, 2009 (text of Article 1169).
Sources rechecked as of: October 19, 2026
This guide gives general information on Philippine civil law, not legal advice. The result in a particular dispute depends on the contract, the evidence and the applicable law.